The Rodanthe bridge is 39% complete and still on track to open in fall 2021. The state’s transportation department held a quarterly update meeting online Thursday, June 4. Pablo Hernandez, NCDOT resident engineer, provided the update on the $145.33 million bridge. Get the latest headlines sent to you Sign up for our free newsletter Overall, … Continue reading Rodanthe bridge update presented by NCDOT