Only a half-mile separates the two parts of the Rodanthe Bridge

The Rodanthe Bridge is 75% complete and NCDOT is aiming to finish the structure by the end of 2021 or the beginning of 2022. Expenditures now total $133.26 million. A half-mile separates the two construction sides of the bridge. That closeness is reflected in the bridge parts already placed: 90 of 108 bents installed with … Continue reading Only a half-mile separates the two parts of the Rodanthe Bridge